- ML112990211 - Forwards binders & sets of divider tabs for use w/NEDO-21888 "Mark 1 Containment Program Load Definition Rept."
- ML112990249 - Forwards EDS Nuclear,Inc list of BWRs & piping sys which could have been impacted by deficient computer program. GE has no record of reanalysis for Cooper piping sys.
- ML112990235 - Forwards Feb 1979 program activity review re Mark I containment program.
- ML112990220 - Forwards Jan 1979 Mark I containment program activity review.Lists meetings held & provides brief task-by-task summary.
- ML112990214 - Forwards NEDO-21885, "Mark I Containment Program,Downcomer Reduced Submergence,Functional Assessment Rept."
- ML112231888 - Forwards NEDO-21885, "Mark I Containment Program,Downcomer Reduced Submergence,Functional Assessment Rept."
- ML112990247 - Forwards summary of EDS Nuclear,Inc resolution/documentation of elbow flexibility error which existed in versions of PISOL piping analysis computer program from Jan-Oct 1969. Review & reanalysis included all work through Dec 1970.
- ML112990208 - Submits Dec 1978 program activity review,comprised of info from selected sections of monthly rept,w/section on contract & billing status removed.Lists meetings held & provides task-by-task activity summary.
- ML11298A080 - Browns Ferry Nuclear Plant, Units 2 and 3 - Follow-up Letter to 10 CFR 50.9, "Completeness and Accuracy of Information," Notification.
Saturday, November 05, 2011
Some new pix; Browns Ferry docs for the past week posted in ADAMS
Monday, October 31, 2011
NRC docs for Browns Ferry 10/22 - 10/29/2011; Lots of pictures from the Spooktacular 5K
- ML11287A036 - LER 11-001-00, for Browns Ferry Nuclear Plant, Unit 2 regarding Core Spray Relay Found in Incorrect Position.
- ML112971527 - M111018 - Briefing on Browns Ferry, Unit 1.
Many pictures (plus the results) of Saturday's Spooktacular 5K can be viewed here...